EcoPro BM Delays Completion of Pohang CAM9 Plant Due to EV Demand Slowdown

Reporter Kim Jisun / approved : 2024-10-23 07:06:39
  • -
  • +
  • 인쇄

(Photo= Yonhap news)

 

[Alpha Biz= Reporter Kim Jisun] EcoPro BM has postponed the completion of its cathode materials plant, CAM9, in Pohang by two years, citing a slowdown in electric vehicle (EV) demand. Initially scheduled for completion in December 2024, the CAM9 plant will now be finished in December 2026, according to industry sources on the 23rd.


The company had announced plans in May 2022 to invest KRW 473.2 billion in the CAM9 plant at its Pohang Campus 4, with the goal of producing next-generation cathode materials, including "NCMX" and "single-crystal" products. The facility was expected to have an annual production capacity of 54,000 tons.

NCMX is a proprietary quaternary cathode material developed by EcoPro BM, incorporating nickel, cobalt, manganese, and an undisclosed "X" material. Single-crystal cathodes, which offer higher energy density, greater fire resistance, and longer life, are also a key focus for major cathode material manufacturers.

 

 

Alphabiz Reporter Kim Jisun(stockmk2020@alphabiz.co.kr)

어플

주요기사

Bomb Threats Target Major Korean Companies Including Samsung Electronics2025.12.19
FSS Raises Consumer Alert to “Warning” Over Secondary Scams Linked to Coupang Data Breach2025.12.19
Final U.S. Defense Authorization Bill Omits Provisions Supporting South Korea-Japan Shipbuilding Cooperation2025.12.19
Controversy Surrounds KT’s Former Outside Director Cho Seung-ah Amid Dual Directorship Issue2025.12.19
Samsung Securities Lowers LG Energy Solution Target Price to KRW 480,000 Amid Contract Cancellations2025.12.19
뉴스댓글 >

건강이 보이는 대표 K Medical 뉴스

HEADLINE

PHOTO

많이 본 기사