Power resumed after a week at Tesla's German plant

Paul Lee / 기사승인 : 2024-03-13 03:01:41
  • -
  • +
  • 인쇄

Tesla logo. (Photo=Tesla)

 

[Alpha Biz=(Chicago) Reporter Paul Lee] Power supply resumed in a week at Tesla's German plant, which was blacked out due to a fire at a nearby power transmission tower.

Power supplier Edith said it connected Tesla's plant and logistics center to its power grid at 8:45 p.m. on the 11th (local time) and later recovered electricity.

Tesla's German plant outside Berlin was cut off from electricity shortly after a fire broke out at a nearby power transmission tower at 5:15 a.m. on the 5th.

Tesla had originally expected electricity to come back on the 17th.

Tesla expects vehicle production to normalize step by step. A German plant spokesman told rbb, "It is still difficult to say how long it will take for production to resume completely."

Tesla expects to lose hundreds of billions of won due to the plant shutdown.

알파경제 Paul Lee (hoondork1977@alphabiz.co.kr)

주요기사

Trump Calls on NATO to Impose Tariffs on China to End Russia-Ukraine War2025.09.15
Hawaiian Airlines to Launch Incheon–Seattle Route on September 132025.09.12
Daewoo E&C Issues Apology and Halts All Construction Work Nationwide Following Fatal Accident2025.09.11
Australia to Invest AUD 1.7 Billion in Reconnaissance and Attack UUV Fleet to Counter China’s Military Expansion2025.09.11
Chevron Poised to Expand Investment in South Korea’s Refining and Petrochemical Industry2025.09.09
뉴스댓글 >